Cutting Vendor Selection Lead Time by 48% via Integrated Procurement
- HL Mando sought to build a single, unified procurement platform to resolve fragmented workflows caused by five decentralized systems across domestic and overseas entities, non-standardized global processes, and an aging web environment.
- Through PI (Process Innovation) consulting, EMRO designed standard procurement processes targeting six global entities—including South Korea, the United States, China, and Europe—while implementing a package-based integrated procurement system alongside a modern web-standard security environment.
- By integrating workflows and streamlining processes within a single system, EMRO dramatically enhanced global procurement efficiency and productivity—achieving a 48% reduction in supplier selection lead time and a 60% decrease in information search time.
WHO?
HL Mando, an Automotive Parts Manufacturer
As a leading automotive parts manufacturer, HL Mando operated its procurement operations across domestic and overseas entities using multiple standalone systems. However, with key processes—such as vendor registration, unit pricing, contracting, and ordering—scattered across systems, inefficiencies such as repetitive data entry and data discrepancies persisted. Furthermore, differing operational frameworks across entities hindered global standardization, while aging system environments posed limitations in improving security and user convenience.
To address these challenges, HL Mando initiated a project to build MAPS, a new procurement system consolidating company-wide procurement processes into a single platform. EMRO provided PI (Process Innovation) consulting to design standardized global processes and implemented a structure capable of handling the entire procurement lifecycle within a single system.
As a result, HL Mando established a foundation enabling six global entities to perform operations under a unified standard process, achieving outcomes such as a 48% reduction in supplier selection lead time and a 60% decrease in information search time. Let's explore the journey of how HL Mando successfully unified its complex decentralized systems and unlocked innovations to elevate its global procurement competitiveness.
Challenges
Non-Standardized Procurement Processes and Limitations in Integrated Management Caused by Decentralized Systems
-
Procurement Process Fragmentation Caused by Five Decentralized Systems
Previously, core procurement tasks—such as new vendor registration, unit price approvals, contract approvals, purchase unit price management, and standard cost management—were operated across separate standalone systems. For instance, workflows required drafting a unit price approval in the pricing system, logging into the contract system to negotiate and finalize agreements with suppliers, and then returning to the pricing system to retrieve the contract and submit a final unit price approval. Because of this fragmented workflow, data integration across systems was not smooth, leading to inefficiencies such as repetitive data entry and risks of human error.
-
Non-Standardized Global Operations and Data Inconsistencies
Because procurement processes and data management standards varied across domestic and overseas entities, processing methods for identical tasks differed by region. As a result, it was difficult to ensure consistency in operational quality and productivity. To address this, standardizing global processes and data was established as a core objective for the project.
-
Aging Security & Technical Environments, and Low User Convenience
The legacy systems operated on Internet Explorer (IE), making security patches impossible and constantly exposing the infrastructure to external hacking risks. Furthermore, individual connections with various external institutions (credit rating agencies, certification authorities, disaster recovery services, etc.) made management overly complex.
Results
Enhanced Procurement Efficiency: 48% Reduction in Supplier Selection Lead Time and 60% Decrease in Information Retrieval Time
-
Supplier Selection Lead Time Reduced by 48% (from 77 Days to 44 Days)
Previously, workflows such as new vendor registration, unit price approvals, contract approvals, and developer selections were handled across separate standalone systems. Consequently, completing the entire process—from vendor registration and selection to pricing determination, contracting, and purchase order dispatch—required logging into multiple independent systems.
In the new system, unit price approvals and contract approvals can be executed sequentially within a single platform, automatically linking vendor information and final unit pricing during contract approval while eliminating duplicate data entry. Furthermore, by removing and consolidating unnecessary workflows, the average duration for supplier selection was shortened from 77 days to approximately 44 days.
-
Improved Data Accessibility via Integrated Search, Reducing Information Retrieval Time by 60%
In the past, checking the status of unit price approvals required logging into the pricing system, navigating to the specific menu, searching for the vendor name, and entering the part number just to view document details.
However, the new system allows users to view all related information—such as document archives, unit prices, and contracts—at once simply by entering the vendor name. This reduced information search time by approximately 60% compared to legacy operations. Additionally, a user satisfaction survey yielded an average score of 3.9 out of 5 regarding improvements in speed and lead time.
-
Securing Scalability Across Six Global Entities via Standardized Procurement Processes
While operational frameworks previously varied by entity, the new system is structured so that all global entities utilize identical procedures and menus based on standardized global procurement processes.
Through role-based and menu-based access control, the architecture allows for the addition of entity-specific features when necessary. This ensures that all global entities maintain consistent operational quality and productivity while preserving the flexibility to respond to local requirements.
Testimonial from the Manager in Charge
"This project is particularly meaningful in that it integrated the entire procurement lifecycle—spanning from vendor registration, unit pricing, and contract approvals to purchase ordering—into a single, seamless workflow. By building upon a highly mature, package-based solution while customizing only what was necessary, we successfully secured both stability and scalability. I believe this achievement was made possible because project members from both HL Mando and EMRO collaborated closely toward a shared goal until the very end."
Next Plan
While specific implementation timelines have not yet been finalized, HL Mando maintains a strong interest in and commitment to adopting artificial intelligence technologies. We plan to gradually explore AI applications across various procurement workflows—such as utilizing small Language Models (sLLMs) for similar-part price comparisons, contract drafting and review, procurement negotiation scenario generation and simulation, supply chain risk sensing, and monthly report generation.